Conwy Valley line to reopen

The Conwy Valley Line in North Wales, which runs from Blaenau Ffestiniog to Llandudno, is due to reopen on 28 September following a £2.2 million project by Network Rail that will help protect the railway from extreme weather and flooding.

Twice in the past two years, the line has been washed away because of flooding, which has meant lengthy closures for passengers and local communities while the railway has been repaired.

The improvements to help protect the line have been entirely designed and built by Network Rail and involve the installation of 16,000 tonnes of rock armour alongside almost 2km of railway between Tal y Cafn and Llanrwst. This will help improve the resilience of the railway during the ever more frequent flooding events in the valley.

This new rock armour slows the water down to prevent it carrying away the railway embankment and leaving the track suspended in the air, which leads to trains being stopped for significant periods.

Damage to the Conwy Valley line caused by storms in February 2020.

The newly protection has already been tested as Storm Francis hit the area at the end of August, when heavy rain meant access to the site was flooded, but the railway itself was not damaged during the extreme weather.

Now the resilience work has been completed, Transport for Wales will carry out driver refresher training following the long closure of the line ahead of services restarting on 28 September.

Bill Kelly, Network Rail’s route director for Wales and Borders, said: “I am delighted that the Conwy Valley line is now better protected as extreme weather has forced it to be closed too often in recent years.

“We have worked around the clock in recent months to not just repair the line, but to make it more resilient so we can help to prevent these long closures in the future.”

Rail Minister Chris Heaton-Harris said: “The Conwy Valley line is a vital link for many local communities in north Wales, and this investment will improve the resilience of that crucial route during extreme weather.

“Upgrading the railway defences will help prevent lengthy closures for passengers, avoid frustrating rail replacement services, and deliver a more reliable timetable people can depend on.”

Recommended

Rail Ombudsman handled 6,500 complaints in two years

The Rail Ombudsman, which is celebrating its second anniversary, is calling upon industry to do more to ensure that passengers are aware...

Network Rail and White Ribbon UK tackle domestic abuse

Network Rail has been approved as a White Ribbon UK-accredited organisation as part of its commitment to changing the behaviour and culture...

Railtex/Infrarail postponed until September 2021

The UK’s major railway industry exhibitions, Railtex 2021 and Infrarail 2021, have been postponed to 7-9 September 2021. The...

Government to fund feasibility work for digital signalling on three more main lines

Rail Minister Chris Heaton-Harris has announced £1.2 million of new government funding to accelerate feasibility work for digital signalling on vital sections...

30 new apprentices for Alstom

Alstom has a long tradition of taking on apprentices, and this year it has welcomed 30 new apprentices to its UK business,...