Transpennine Route Upgrade summer 2021

Listen to this article

Network Rail has announced its plans for the first tranche of its Transpennine Route Upgrade (TRU) programme. The work forms part of TRU’s wider goal to deliver sought-after improvements along the full 76-mile Transpennine route – stretching from York to Manchester, via Leeds and Huddersfield.

This summer, work will take place east of Manchester Victoria station, closing the lines towards Stalybridge and Rochdale, with a 16-day railway closure between these destinations from the 31 July to 16 August 2021.

During the 16-day closure, hundreds of railway workers will be working day and night to renew key sections of track, including around Miles Platting, and upgrading railway bridges to improve reliability. This important work is the first step to enable wider improvements that are expected to bring much needed benefits to passengers.

The planned closure means that, from 31 July, there will be no trains between Manchester Victoria and Stalybridge and Manchester Victoria and Rochdale until these lines reopen on 16 August.