HomeIndustry NewsMilestone met at HS2 green tunnel

Milestone met at HS2 green tunnel

Listen to this article

Construction of HS2’s longest green tunnel took a major step in early December with the realignment of a key local road, freeing up space for the next phase of excavations.

Set to stretch for 2.7km, the tunnel is being built inside a shallow cutting near Greatworth, West Northamptonshire, using a ‘cut-and-cover’ technique, with the earth put back on top afterwards. This helps to blend the railway into the landscape.

Engineers working for the high-speed rail project have already assembled the first kilometre of the structure and the temporary realignment of the B4525 will allow work to begin on the next stage of the tunnel.

Assembled from precast concrete segments, the tunnel is in an ‘M’ shape, with separate halves for northbound and southbound trains. Inspired by similar structures on the French high-speed network, the approach promised to be quick to assemble, with much of the work done offsite.

The nearby Chipping Warden green tunnel uses a similar design and the teams at the two tunnels have been able to learn lessons from each other.

Work began first at Chipping Warden where it quickly became clear that the initial construction schedule was overly optimistic with the team facing significant productivity challenges.

Recognising the need to improve productivity, HS2 Ltd worked closely with their main works contractor EKFB – a group made up of Eiffage, Kier, Ferrovial Construction, and Bam Nuttall – to identify and put in place a series of improvements to the construction process.

As a result, the teams at both tunnels are now installing around five to six segments per day – more than double the rate at Chipping Warden during the start of work in 2022/23.

HS2 Ltd’s project manager, Sam Arrowsmith, said: “I’m really pleased to see the temporary realignment of the B4525 open to drivers. This major milestone means that we can keep local traffic moving while we deliver the next stage of the Greatworth green tunnel.

“Once complete, the tunnel will help protect the rural landscape and reduce disruption for people living nearby. We’ve still got a long way to go, but the lessons from Chipping Warden have helped us significantly increase productivity and I’d like to thank everyone who’s worked so hard to get us to this point.”

The construction of the tunnel is happening in stages, with the cutting first being excavated and then a layer of ‘blinding’ laid to form a concrete base for the structure. To speed up the blinding process, the steel reinforcing bars are now being delivered as a ‘roll mat’ with the parallel bars connected by mild steel tape so they can be quickly rolled out ready for the concrete pour.

The next stage involves the assembly of the five concrete segments that form each of the ‘M’ shaped sections of tunnel. Continual improvements have been made to the delivery and installation process to improve the speed and accuracy of the assembly and cut unnecessary waiting time.

Once the structure has been assembled, a concrete ‘invert’ slab is poured to form the base for the track. This process has been sped up by changing the direction from which concrete is delivered and by introducing prefabricated reinforcing cages which has doubled the speed of the work.

Image credit: HS2

Recommended